Crystalline Silicon PV Module Installation Manual
1. Introduction
1.1 Purpose
1.2 Limitation of Liability
1.3 Precautions for Installation
2. Safety
2.1 General Safety
2.2 Installation Safety
3. Mechanical Installation
3.1 Installation Condition
3.2 Installation Methods
4. Electrical Installation
4.1 Installation Condition
4.2 Grounding
5. Maintenance

Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
1. Introduction
1.1 Purpose
This document provides detailed instructions and valuable safety information regarding the
installation, electrical connection, and maintenance of following Chint Solar Crystalline Photovoltaic
modules:
CHSM60M(DG)/F-B CHSM60M(DGT)/F-B CHSM72M(DG)/F-B CHSM72M(DGT)/F-B
CHSM60M(DG)/F-BH CHSM60M(DGT)/F-BH CHSM72M(DG)/F-BH CHSM72M(DGT)/F-BH
All the instructions should be read and understood before installation. The installers should
be trained and conform to all safety precautions in this guide when installing the module. Keep
this guide in a safe place for further reference.
1.2 Limitation of Liability
Because the use of this manual and the conditions or methods of installation, operation, use
and maintenance of photovoltaic (PV) products are beyond Chint Solar’s control, Chint Solar
does not afford the responsibility and expressly disclaims liability for loss, damage, or expense
arising out of or in any way connected with such installation, operation, use or maintenance.
Chint Solar reserves the right to change the manual without prior notice.
1.3 Precautions of Installation
1.3.1 Module’s unpack and transfer
a) When the whole pallet of modules are delivered to the site and unloaded, make sure the
safety of the modules especially if they need to be lifted for roof projects. Put them into a
protective device and then lift it to the roof in case of bumping against the wall during the
lifting process.
b) Firstly, tear the stretch film, then move away the top cover after cutting off each module
packing strip while unpacking. Two operators work as a group, grasp the module frame
tightly in the same direction and take out the module one by one. It is a must that the
operators remove the adhesive tape of the fixed module one by one, rive one piece and
then take out one piece of module. We don’t allow to tear off all the adhesive tape at one
time to prevent the whole package from toppling over or falling down. The whole process
must be taken very gently. Don’t collide with any hard objects or let any parts of the frame
touch and drag on the ground.
c) After unpacking the modules should be installed that day as far as possible. It’s

Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
recommended to take the right amount of modules according to the progress of the project
every day. Heavy rain and other inclement weather may have the potential to soak the
packaging which can affect product reliability, such as storms, typhoons, hurricanes or other
events in which they may be blown away. If the users need to store modules before
installation, do not open the package, the goods should be stored in a room temperature,
dark, dry and ventilated place.
1.3.2 Module’s Stack
a) When a module is taken out of the box, cardboard bedding below should be applied in order
to avoid contact with cement surface / ground, hard metal or tile. Modules should be placed
neatly and should not be dropped, slammed or scratched.
b) When stacking modules, it needs to be stacked neatly in the horizontal plane, under the
condition of the glass facing down and the back way piled up, while the cardboard bedding
need to be underside the modules. If the modules will be installed on the rooftop, the
number of each stack is suggested no more than 20. In case of the poor load-bearing
capacity, it’s recommended that the designer and/or installer check with the structural
engineer or architect to determine the amount of load allowable for specific location. During
the whole process, the installation tools and other objects must be prevented from
contacting the module surface.
c) If the modules are requested to be classified by current, the handling personnel are required
to carry out of the level of the current and make a mark separately according to the power
on the list. (e.g. 275W-L, identifies the modules of the packaging according to the power on
the list, indicating a low current position; 275W-H, compared to high current position).
Usually, the same series of modules in the same current position are required in
accordance with the system design requirements.
d) If the modules are color-coded and marked the corresponding logo on the carton due to the
customer requirements, when modules are taken out and stacked, they should be labeled to
avoid confusion. Usually the same row or the same square have the same color according
to the system design requirements.
e) Due to the complexity and difference of the construction site, these precautions may not
cover all items, please refer to the specific construction standards.

Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
2. Safety
2.1 General Safety
2.1.1 Consult and follow local codes and other applicable laws concerning required permitting
as well as installation & inspection requirements, rules, and regulations.
2.1.2 PV modules should be installed and maintained by qualified personnel.
2.1.3 Use the same performance modules within a given series.
2.1.4 Follow all safety precautions of all components used in the system.
2.1.5 Do not shade portions of the PV module surface from the sun for a long period of time.
The shaded cell may become hot (hot spot phenomenon), which can result in solder joints
peeling off.
2.1.6 Do not clean the glass surface with chemicals.
2.1.7 Do not drop the PV module or drop objects onto the PV module.
2.1.8 Do not concentrate sunlight on the modules or panels.
2.1.9 Do not attempt to disassemble the modules, and do not remove any attached components
from the modules.
2.1.10 Do not scratch or hit at the back sheet, the glass, the terminal box. Do not pull the cables
or touch them with bare hands.
2.1.11 Do not drill holes in the frame or scratch the anodized film of the frame.
2.1.12 Keep the PV module packed in the carton until installation.
2.1.13 Do not use modules near equipment or in places where flammable gases may be
generated.
2.1.14 Do not use modules in an environment with aliphatic, aromatic, phenols, ketones,
halogenated substance or mineral oil, which may corrode the junction box by chemical
attack.
2.2 Installation Safety
2.2.1 Wear protective clothing such as head gear, insulating gloves, safety shoes as prescribed
by local safey codes. Use insulated tools when installing the modules.
2.2.2 Do not install the modules in heavy rain, snow, or otherwise wet or windy conditions.
2.2.3 Completely cover the PV module surface with an opaque material during PV module
installation and wiring to prevent accidental charge buildup.
2.2.4 Plug in connectors tightly when working on wiring.
2.2.5 Due to the risk of electrical shock, do not perform any work if the terminals of PV module
are wet.
2.2.6 Do not touch the terminal box and the end of output cables (connectors) with bare hands.

Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
2.2.7 Do not unplug the connector under load.
2.2.8 Do not work alone.
2.2.9 Wear a safety harness if working far above the ground.
2.2.10 Do not wear metallic jewelry, which can cause electric shock, while installing or
troubleshooting the PV system.
2.2.11 Follow the safety regulations for any and all other system components, including wires,
connectors, charging regulators, batteries, inverters, etc.
2.2.12 Do not expose wires to direct sunlight. Use UV-resistant cable.
2.2.13 Do not damage the surrounding PV modules or mounting structure when replacing a PV
module.
2.2.14 Do not change any PV module components (diode, junction box, connectors, etc.).
2.2.15 The maximum reverse current is 27A for bifacial module. Application of the blocking diode
and fuse in the combiner box are recommended for reverse current protection when more
than two strings are connected in parallel.
2.2.16 A certain gap is maintained between the PV module and the mounting surface to prevent
the mounting surface touching the junction box.
2.2.17 Standing on the solar PV module is forbidden and also prohibit installation tools or other
objects hitting surface of the solar PV module.
2.2.18 The solar modules are recommended to be installed over a fireproof and insulating roof
covering when installed on a roof.
2.2.19 PV cable connection cannot be too tight, it is recommended that the connector and the
backsheet have a certain gap.
2.2.20 In sandy regions, in order to avoid getting sand into the connector, we suggest to short
circuit module connectors before installation. If grains of sand get into the connectors it,
may cause internal live parts wear and tear and affect electrical safety.
3 Mechanical Installation
3.1 Installation Conditions
3.1.1 Extreme environment temperature:-40℃ to +85℃
3.1.2 Operating temperature:-40℃ to +85℃
3.1.3 Mechanical load on panels (e.g., snow/wind): The max tested snow/wind load is
5400Pa/2400Pa, and the design load is 3600Pa/1600Pa with a safety factor 1.5 under
standard mounting system. Please refer to the detailed mounting instructions as Chapter
3.2.
3.1.4 Tilt Angle selection: The installation should be facing north in the southern hemisphere
and facing south in the northern hemisphere.
3.1.5 To maintain the modules’ Class A fire rating, the fire class of the roof and building

Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
materials should be higher than Class A.
3.1.6 To maintain the modules’ fire performance type 3(for US market), it could be possible to
achieve the Class A system fire rating, with the Class A class racking system.
3.2 Installation Methods
3.2.1 Bolting through the mounting holes
① All modules must be secured by at least 4 bolts (as shown in figure 1 and 2). For maximum
safety precaution, it is recommended to make use of all installation holes available, as shown
in figure 3.
② While installing, the module frame should be parallel to the mounting rack to avoid casting
shadow on the rear side, as shown in figure 4.
Figure 1 Figure 2
Figure 3 Figure 4
Note: the red arrows above is indicative of the bolts’ location. The installation steps are as
follows ( figure 5 ):
1. Place the module underneath the mounting rack.
2. Insert 4 stainless bolts (M8) into the mounting holes in figure 1 or 2.
3. Make sure that each bolt is installed with two washers, one on each side of the rack. then
screw them tight onto spring washer or toothed washer, and at last, lock them with stainless
nuts.
4. The reference value of tightening torques should be within 17~23 Nm for M8 bolts. For the
torque value, recommendations from specific clamping hardware suppliers should prevail.

Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
Figure 5
3.2.2 Clamping on the frame surface
3.2.2.1 Double glass module
During the installation of bifacial modules, the frame and mounting rack should
maintain parallel, as shown in figure 6 and figure 7.
Figure 6

Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
Figure 7
Remark:
1) The length of supporting bars must be longer than the length of module frame, otherwise
please confirm with our product team to get approval.
2) As for above figure 6, the solid red rectangles indicate primary clamp installation positions
and the center positions of long frames where clamps can be added for additional support.
3) As for above figure 7, “ ” indicates the allowable installation range of the aluminum clamp,
the recommended installation location is 50~200mm. For this installation, the module's maximum
mechanical test load is 1200Pa for positive and negative.
4) The above figures illustrate the proper installation method of frame surface clamp. “L±100”
indicates its mounting location, as specified as follows:
Module type Dimensions L±100
L*W*H (mm)
CHSM60M(DG)/F-B 1664*998*30 350
CHSM60M(DGT)/F-B
CHSM72M(DG)/F-B 1980*998*30 450
CHSM72M(DGT)/F-B
CHSM60M(DG)/F-BH 1696*998*30 350
CHSM60M(DGT)/F-BH 1714*1010*30
CHSM72M(DG)/F-BH 2018*998*30 450
CHSM72M(DGT)/F-BH 2038*1010*30

Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
5) Each aluminum clamp is equipped with a M8 bolt, a plain washer, a spring washer and a M8
nut, to fasten the module:
a) Place the module on the two supporting bars (not provided). The bars should be made with
stainless material and treated with an anti-corrosion process (e.g., anodic oxidation
treatment) or aluminum profile. Each solar PV module needs at least four clamps to fix. Do
not make the clamp contact the glass directly or make the aluminum frame deformation in
the installation process, and avoid the shadow of solar PV components.
b) The bar’s top surface contacted with module frame should come with grooves compatible
with an M8 bolt.
c) If the bars do not come with grooves, holes of a suitable diameter may need to be drilled to
allow bolts to be attached to the bars at the same locations as mentioned above.
d) Secure each clamp by attaching plain washer, spring washer, and nut, in that order.
e) Both of close-ups of Figure 8, indicating the middle clamps and Figure 9, indicating the side
clamps for reference. Suggest the dimensions for middle clamps are: a ≥ 40 mm, b ≥ 26 mm,
c = 8 mm, d ≥ 28 mm, and Ø = 9 mm. The torque for tightening the nut and bolts are
recommended 17~23Nm when the property class of bolts and screws is Class 8.8.
Figure 8
Figure 9
f) For figure 6 mounting method, the modules must be supported along the length of the edge,
and should overlap the array rail by 10mm – 14mm, as shown in figure 10.
Figure 10

Chint Solar (Zhejiang) Co.,Ltd. | Add:1335 Bin´an Road, Binjiang District, Hangzhou | P.C: 310053
Tel: 0086-571-5603 1888 | Fax: 086-571-5603 2316 | Website: http://energy.chint.com/
4 Electrical Installation
4.1 Installation Condition
4.1.1 The electrical characteristics are within ±10% of the indicated values of Isc. Voc and
Pmpp under the standard test conditions (irradiance of 1000 W/m2, AM1.5 spectrum, cell
temperature of 25℃.
4.1.2 The IEC & UL standard maximum system voltage for the bifacial module series is 1500V.
4.1.3 Connect quantity of modules that match the voltage specifications of the inverters used in
system. Modules must not be connected together to create a voltage higher than the
permitted maximum system voltage under the lowest local temperature conditions.
4.1.4 Under normal conditions, a photovoltaic module is likely to experience conditions that
produce more current and/or voltage than reported at standard test conditions.
Accordingly, the value of Isc marked on this module should be multiplied by a factor of 1.25
when determining component conductor ampacities, fuse sizes, and size of controls
connected to the PV output.
4.1.5 Refer to Section 690-8 of the National Electrical Code for an additional multiplying factor
of 125%(80% derating) which may be applicable.
4.1.6 Each module (or series-connected string of modules) shall be provided with the maximum
series fuse, specified 20A for bifacial module.
4.1.7 Use a special solar cable and plugs for installing the PV system and make sure that all
connections are safe and tight. The cable should be 4 mm2 (12AWG), and able to
withstand the maximum possible system open-circuit voltage.
4.1.8 Bypass diodes are included in module junction boxes to avoid decreased module
performance in the event of shade. Please check the relevant product datasheet for the
specific diodes of J-box.
4.1.9 Prohibit interconnection between different types of connectors.
Dieses Handbuch passt für folgende Modelle
11
Inhaltsverzeichnis
Andere Astronergy Solarpanel Handbücher

Astronergy
Astronergy ASM6610 Series Bedienungsanleitung

Astronergy
Astronergy CHSM60M(DG)/F-B Bedienungsanleitung

Astronergy
Astronergy CHSM5001T Bedienungsanleitung

Astronergy
Astronergy CHSM6610M Bedienungsanleitung

Astronergy
Astronergy CHSM72M-HC Bedienungsanleitung

Astronergy
Astronergy CHSM6610M Bedienungsanleitung

Astronergy
Astronergy CHSM54M-HC Bedienungsanleitung

Astronergy
Astronergy CHSM6610M Bedienungsanleitung