Chapter I: Technical Data 4
1 Dimensions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2 Intended purpose. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3 Fuel quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
4 Execution of the boiler room . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
5 Design of the fuel storage room. . . . . . . . . . . . . . . . . . . . . . . . . . . 5
6 Execution of heating circuits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
7 Flue pipe - chimney connections . . . . . . . . . . . . . . . . . . . . . . . . . . 6
8 Electrical supply. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Chapter II: Safety regulations 7
1 General safety advices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
2 Remaining risks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
3 Measures in case of danger . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Chapter III: Operation 11
1 Overview of components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
2 Prior to commissioning. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
3 Control panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
4 Operating modes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
5 Boiler's status indicators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
6 Info - menu . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
7 Manual operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
8 Settings menu . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
9 Customer settings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
10 Installer settings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
11 Optional remote controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
Chapter IV: Cleaning, Maintenance 51
1 Maintenance contract . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
2 Cleaning and maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
3 Disposal information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
Chapter V: Troubleshooting 58
1 Error display. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
2 Retrieving the error list . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
3 Acknowledging and rectifying an error . . . . . . . . . . . . . . . . . . . . 58
Chapter VI: Appendix 59
1 Copyright notice. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
Declaration of Conformity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60

HARGASSNER Heating technology for Biomass A 4952 Weng OÖ Tel.: +43/7723/5274-0 Fax: +43/7723/5274-5 [email protected] 3
Dear customer!
You've chosen an innovative wood biomass boiler from Hargasssner. The boiler
from Hargassner Ges mbH is a state of the art product and manufactured to the
latest production standards. We are very pleased about your decision and guar-
antee that you've chosen a reliable quality product.
However, as important as the products' high performance is, a professional instal-
lation, commissioning and service is just as crucial. Supportive are attached
hydraulic schematics, and connections- and installation drawings. To ensure a
long service life, exactly read and follow this operation manual. High costs for
reparation and long downtimes may be prevented.
Keep this manual within easy reach.
The operating manual is intended to help:
• become familiar with the boiler
• and to use it for its intended purpose.
This operation manual contains important information in order to operate the
boiler
• safely
• appropriately
• efficiently
• and economically
Guidelines within this manual will:
• Prevent hazards
• Reduce breakdowns and wear
• Increase the reliability and service life of the boiler

4HARGASSNER Heating technology for Biomass A 4952 Weng OÖ Tel.: +43/7723/5274-0 Fax: +43/7723/5274-5 [email protected]
I Technical Data
Chapter I: Technical Data
1 Dimensions
2 Intended purpose
This automatic wood pellet boiler is designed to heat water only. Only fuels
permitted by Hargassner may be burned in this boiler. Only use the boiler if it is
in technically perfect condition. Rectify errors immediately.
The appropriate operation also covers observation of all items of this operation
manual and the carrying out of inspection- and maintenance works.
3 Fuel quality
Only use fuels that comply with EN ISO 17225-2 (replaces ÖNORM EN 14961-2).
3.1 Wood Pellets (A1)
Ensure these quality standards are adhered to when wood pellets are ordered and
delivered.
• Least possible dust content
• Wood pellets with a hard and shiny surface
• 100% natural wood, no additives, etc.
• Wood pellet class A1 defined in EN ISO 17225-2:2014 and
ÖNORM M 7136
B
H
T
Designation Description Value Unit
B Total width 1165 mm
T Total depth 775 mm
H Total height 1470 mm
Total weight 300 kg
W A R N I N G
Only use released and permitted fuels
Always consult Hargassner before using new fuels.
Have their compatibility with the boiler checked by Hargassner.
Calorific
value Density Diameter Length Fine material
rate
> 4.6 kWh/kg 600 - 750 kg/m³ 6 ±1 mm 3.15 - 40 mm < 1%

I
HARGASSNER Heating technology for Biomass A 4952 Weng OÖ Tel.: +43/7723/5274-0 Fax: +43/7723/5274-5 [email protected] 5
Technical Data
3.2 Inadmissible fuels
• Fuels with water content >35%
Formation of condensate
Increased corrosion in the boiler
• Paper / Cardboard
• Chip boards, impregnated timber
• Black coal, brown coal or lignite
• Waste
• Plastics
4 Execution of the boiler room
Boiler room must executed according to legislation in your country.
See "Design of the boiler room" in the installation manual
• Keep the boiler's air openings free.
• Do not store any flammable materials in the boiler room.
• Execute the boiler room in frost-proof condition.
• fireproof, plane and solid floor- and ceiling construction
• In accordance with regulations, have the main heating switch installed by an
electrician (depending on building regulations).
• Fire extinguisher
5 Design of the fuel storage room
Design your pellet fuel storage room in accordance with local regulations
(e.g. ÖNORM M 7137 or VDI 3464).
See "Design of the fuel storage room" in the installation manual
• Only install metal fill pipes, electrically grounded and connection to atmosphere.
• Pay attention to noise protection
• Protection against moisture, water and dust.
• Correctly position impact protection mat(s) and install slant floor.
6 Execution of heating circuits
The heating circuits must be designed correctly for optimum operation of the boiler.
Authorised heating diagrams: See heating diagrams enclosed.
The layout of the heating circuits' accumulators, pumps and mixers has to be
designed according to legislation by the installer.
D A N G E R
Danger of suffocation due to odorless carbon monoxide in the storage room
• Ventilate sufficiently before entering the fuel storage room
• Keep window/door open during stay
• Position second person outside to supervise
Dust explosions in the storage room due to the explosive combustion of
dust (pellet dust)
• Pay attention to proper grounding of the pellets transportation tubes
• No motors in the fuel storage room
Except agricultural buildings
• No other source of ignition (e.g. light) in the storage room
• No electrical equipment (e.g. light switch) in the storage room
• No welding works in dusty environment

6HARGASSNER Heating technology for Biomass A 4952 Weng OÖ Tel.: +43/7723/5274-0 Fax: +43/7723/5274-5 [email protected]
I Technical Data
7 Flue pipe - chimney connections
8 Electrical supply
See according to enclosed electrical manual
• The electrical connection may only be established by a licensed and authorised
electrician and must be done in accordance with the enclosed electrical manual.
• Attach a lockable main power switch outside of the boiler room (depending on
building regulations).
• Max. prefuse 13 A (C characteristic)
• It is absolutely imperative that the intrinsically safe cables are permanently installed
• Use suitable mechanical components
• in-phase connection L and N (see electrical manual)
• Connect potential equalisation
• Use highly flexible cables (e.g. H05VV-F)
Description Unit Classic 12 Classic 14 Classic 15 Classic 22
Nominal heating output KW 12.0 14.9 15.0 22.0
Flue gas temperature °C 150 150 150 150
CO2% 14
Mass volume kg/Sec 0.0071 0.0082 0.0088 0.0129
Necessary pressure Pa 2
Flue draft max. limit Pa 10
Diameter of flue pipe connection mm 130
Water resistance dT 10° mbar 6.2 7.2 7.7 18.3
Water resistance dT 20° mbar 2.0 2.3 2.5 3.8
Electrical energy Characteristics Unit
Voltage 230 V ± 5 %
Frequency 50 Hz ± 5 %
Fuse 13 A
Power consumption 47 W

II
HARGASSNER Heating technology for Biomass A 4952 Weng OÖ Tel.: +43/7723/5274-0 Fax: +43/7723/5274-5 [email protected] 7
Safety regulations
Chapter II: Safety regulations
1 General safety advices
1.1 Obligation to instruct, external personnel, children
Work on electrical parts of the boiler may only be carried out by an electrician and
in compliance with the electro-technical rules and standards.
Work on hydraulic systems may only be carried out by personnel with specialised
knowledge and experience in heating engineering and pipework construction.
1.2 Special measures prior commissioning through the operator
• Licensing requirements for safe operation and accident prevention regulations
must be observed!
• Do execute verifications prior first start up.
See „Checks prior commissioning“ on page 12.
• Do execute verifications prior commissioning.
See „Inspections prior starting up the boiler“ on page 13.
D A N G E R
Risk of death, injuries, damage from inappropriate installation
• Observe the safety instructions of the boiler and in the operation manual!
• Read the user manual PRIOR to commissioning.
In the cladding door is a storage compartment
Incorrect actions by unauthorized individuals
• Works on the boiler through qualified and experienced personnel only.
• Decide who is responsible for managing the boiler.
• Keep external, unauthorised and untrained people away from the boiler and the fuel
storage room
• No transfer of control entry codes
• Observe legal minimum age of personnel.
• Place prohibition sign in front of boiler room door and fuel storage door.
Risk of suffocation due to odourless carbon monoxide
• Ventilate sufficiently before entering the fuel storage room
• Keep window/door open during stay
• Always have a second person outside to supervise.

8HARGASSNER Heating technology for Biomass A 4952 Weng OÖ Tel.: +43/7723/5274-0 Fax: +43/7723/5274-5 [email protected]
II Safety regulations
2 Remaining risks
The following residual risks must be given special consideration when the boiler
is operated properly and in accordance with its intended purpose:
D A N G E R
Burns from hot surfaces or boiler components
• Switch off the boiler and let it cool down before carrying out any maintenance or ser-
vicing work
• Do not grasp into the boiler during operation.
• Wear heat resistant gloves.
The ash in the ash box does save heat.
• Put ash in closed, not-flammable vessels only.
Do not empty hot ash into dustbin
Scalds from sprinkling, hot water
• Check hoses, lines and connections periodically for leakages, wear and tear or any
other damage!
• Rectify damages immediately.
• Before performing any maintenance work on the water circulation system, depres-
surise the boiler.
• Check, if all valves are in correct position.
D A N G E R
Dust explosion due to electro-static charging in the fuel storage room
• Pay attention to proper grounding of the pellets transportation tubes
• No motors in the fuel storage room (acc. to country-specific regulations)
Except agricultural buildings
• No other source of ignition (e.g. light) in the storage room
• No electrical equipment (e.g. light switch) in the storage room
• No welding works in dusty environment
D A N G E R
Burns from explosive combustion of residual gases (CO) in the combus-
tion chamber
• Open the maintenance door carefully.
Slightly in the beginning.
Keep your body and face away from the maintenance door.
• Do not open the maintenance doorduring or straight after a power blackout.
The risk of deflagration increases significantly after uncontrolled conditions.
(e.g. power loss)
• Do not open the maintenance door during heating operation.

II
HARGASSNER Heating technology for Biomass A 4952 Weng OÖ Tel.: +43/7723/5274-0 Fax: +43/7723/5274-5 [email protected] 9
Safety regulations
D A N G E R
Risk of injury due to moving parts
• Omit access to augers or motors at operating boiler.
• Do not perform any work on the boiler when any person is in the danger zone
Secure / lock fuel storage room
• Only clean the augers and remove blockages using suitable tools and when the
main power switch is turned off.
• Wear safety shoes
• Observe fuel storage room sticker!
D A N G E R
Electric shock from contact with live terminals
• Observe information signs.
• Before starting work, check that no voltage is present using a voltmeter
D A N G E R
Poisoning and danger of suffocation due to flue gases in the boiler room / building
• Check boiler doors and seals for leaks.
• Burning treated wood (paint, varnish, impregnation) results in toxic ash.
Avoid skin and eye contact
W A R N I N G
Risk of injury due to unexpected operating statuses
• During manual mode no monitoring of limit switches or motors is performed.
Only run the augers backwards briefly (two seconds maximum).
• Manual mode is only allowed to be executed by trained staff.

10 HARGASSNER Heating technology for Biomass A 4952 Weng OÖ Tel.: +43/7723/5274-0 Fax: +43/7723/5274-5 [email protected]
II Safety regulations
3 Measures in case of danger
3.1 Fire in the boiler room
Switch-off main switch prior any fire-fighting operations
Disconnect main power supply
Switch-off the boiler and unplug the unit from the mains
3.2 After power loss
During the power failure, do not open the boiler's doors or reach into it.
Danger of deflagration
Danger of crushing through augers
After the electrical supply is switched on again, the control starts in Heat up mode
and monitors the flue gas temperature.
As the flue gas temperature increases, the boiler will heat up and control the
transfer of heat according to the preset parameters.
3.3 Leak in heating water system (no water)
If the water pressure is too low, not enough heat is being transferred from the
boiler to the heat circuits, HWT and accumulator.
Danger of boiler overheating
Turn off the boiler.
Fix leakiness
fill / refill water system
Check water pressure
3.4 Leak in the boiler (smoke escaping)
Turn off the boiler.
Check the seals of the doors and cleaning covers, and have them replaced.
3.5 Auger blockage(s)
Do not touch the augers.
Danger of crushing at sudden release of blockages
Briefly run the blocked augur backwards in manual mode (two seconds
max.).
Danger of squeezing of fuel in the auger
Only clean the augers and remove blockages using suitable tools and when
the main power switch is turned off and locked
Dieses Handbuch passt für folgende Modelle
3
Inhaltsverzeichnis
Beliebte Kessel Handbücher anderer Marken

Vaillant
Vaillant uniSTOR VIH SW GB 500 BES Bedienungsanleitung

Radijator
Radijator BIO max 23.1 Bedienungsanleitung

Brunner
Brunner BSV 20 Bedienungsanleitung

Buderus
Buderus Logamax GB062-24 KDE H V2 Bedienungsanleitung

Potterton
Potterton 50e Datenblatt

UTICA BOILERS
UTICA BOILERS TriFire Bedienungsanleitung