UfiSpace S8901-54XC Handbuch

Hardware Installation Guide
S8901-54XC
Data Center ToR/Leaf Switch
R1.1

S8901-54XC Hardware Installation Guide | i
Table of Contents
1Overview.............................................................................................................................1
2Preparation.........................................................................................................................2
Installation Tools......................................................................................................................2
Installation Environment Requirements..................................................................................3
Preparation Check List.............................................................................................................4
3Package Contents................................................................................................................5
Accessory List...........................................................................................................................5
Component Physical Information............................................................................................6
4Identifying Your System.......................................................................................................7
S8901-54XC System Overview.................................................................................................7
DC Version PSU Overview........................................................................................................8
AC Version PSU Overview........................................................................................................9
Fan Overview .........................................................................................................................10
Port Overview ........................................................................................................................10
5Rack Mounting..................................................................................................................11
6Installing Fan Modules.......................................................................................................13
7Installing Power Supply Units ............................................................................................14
8Grounding the Switch........................................................................................................16
9Connecting Power .............................................................................................................18
DC Version..............................................................................................................................18
AC Version..............................................................................................................................19
10 Verifying System Operation...............................................................................................20
Front Panel LED....................................................................................................................20
PSU FRU LED ........................................................................................................................21
Fan FRU LED.........................................................................................................................21
Management Port LED.........................................................................................................21
11 Initial System Setup...........................................................................................................22
12 Cable Connections.............................................................................................................23
Connecting the USB Cable ...................................................................................................23
Connecting the OOB Management Cables..........................................................................23
Connecting the Transceivers ...............................................................................................24
13 Cautions and Regulatory Compliance Statements ..............................................................25

S8901-54XC Hardware Installation Guide | 1
1Overview
The UfiSpace S8901-54XC is a high-performance, versatile open networking white box
switch that is designed to provide data center the needed connectivity required from
different servers and devices.
With a small form factor and high-density configurations, the S8901-54XC switch is a white box
switch that can be positioned as a ToR (Top-of-Rack) or leaf switch to enable versatile connectivity
and traffic management. It comes with redundant, hot swappable components for convenience,
increased availability, reliability and lower costs of maintenance.
This document describes the hardware installation process for S8901-54XC.

S8901-54XC Hardware Installation Guide | 2
2Preparation
Installation Tools
Phillips #2 Screwdriver
Crimping tool
14-AWG wire with ring terminal for
DC power supply
6-AWG wire for grounding
Wire-stripping tools for
stripping 6-AWG copper wire
Console cable
•PC with terminal emulation software. Refer to the "Initial System Setup" section for
details.
•Baud rate: 115200 bps
•Data bits: 8
•Parity: None
•Stop bits: 1
•Flow control: None

S8901-54XC Hardware Installation Guide | 3
Installation Environment Requirements
•Power Reserve: The S8901-54XC power supply is available with:
1. DC Version: 1+1 active-active -36 to -75V DC power supply field replaceable unit or;
2. AC Version: 1+1 active-active 100 to 240V AC power supply field replaceable unit.
To ensure the active-active feed power design functions properly, a field with dual power
circuit is recommend with a reserve of at least 450 watts on each power circuit.
•Space Clearance: The S8901-54XC width is 17.32 inches (44.0cm) and shipped with a rack
mount brackets suitable for 19 inch (43.8cm) wide racks. The depth of the S8901-54XC chassis
is 17.32 inches (44cm) without the field replaceable units (FRUs) and comes with adjustable
mounting rails suitable for rack depths of 22 inches (55.9cm) to 33 inches (83.8cm). The
handle for the fan units will extend outwards by 1 inch (2.5cm) and the handle for the power
supplies will extend outwards by 1.5 inches (3.8cm). Therefore, to accommodate the fan and
power supply handles, a minimum space clearance of 6 inches (15.24cm) is needed at the
back of the S8901-54XC. A total minimum reserve depth of 23.32 inches (59.23cm) is
required.
Figure 1.
Figure 2.

S8901-54XC Hardware Installation Guide | 4
•
Cooling: The S8901-54XC has two options for airflow direction. There is a back-to-front
option (Figure 3. Left) and a front-to-back option (Figure 3. Right). Make sure the
equipment on the same rack have the same airflow direction.
Back-to-Front Airflow
Front-to-Back Airflow
Figure 3.
Figure 4.
Preparation Check List
Task
Check
Date
Power voltage and electric current requirement
DC version: -36 to -75V DC, 16A maximum x2 or;
AC version: 100 to 240V, 6A maximum x2
Installation spacing requirement:
S8901-54XC spacing requires a height of 1RU (1.72”/4.5cm), a width
of 19” (48cm) and a depth of 17.32 inches (44cm)
Thermal requirement
S8901-54XC working temperature is 0°C to 45°C (32°F to 113°F)
Installation tools required
#2 Phillips Screwdriver, 6-AWG wire stripper, and crimping tool
Accessories required
PC with terminal emulation software, console cable, 14-AWG wire
with ring terminal for power, 6-AWG wire for grounding
Rear wall clearance = 6”

S8901-54XC Hardware Installation Guide | 5
3Package Contents
Accessory List
Item
Description
Spec. & Dimensions
Qty.
Weight
1
Grounding kit for
system
1 x Grounding Lug (#6 AWG)
1.14” x 1.47” x 0.49”
(29 x 37.5 x 12.5mm)
2 x Screw: M4*L8.0mm
2 x M4 Lock Washers
1 set
0.037lb (17.0g)/set
2
Rack Mount Bracket
2.56” x 1.69” x 0.79”
(19” width rack)
(65x 43 x 20mm)
2 pcs
0.27lb (124g)/2pcs
(0.14lb (62g)/pcs)
3
Screw Kit (for Rack
Mount Bracket)
8 x Screws M4.0*L6.5mm
1 set
0.02lb (7g)/set
4
Adjustable Mounting
Rail (for 4 posts)
16.02” x 1.69” x 0.83”
(406.8 x 43 x 21mm)
(for 22” to 33” rack depth)
2 sets
1.39lb (630g)/2 set
(0.69lb (315g)/set)
5
Screw Kit
(for Adjustable
Mounting Rail)
8 x Screws M4.0*L6.5mm
1 set
0.02lb (7g)/set
6
Power Cord
(AC Version only)
72.05” (1830mm)
2 pcs
1.43lb (650g)/2pcs
0.72lb (325g)/pcs
7
USB 3.0 cable
7.87” (200mm)
1 pcs
0.038lb (17.2g)/pcs
8
RJ45 to DB9 Female
Cable
95.98” (2438mm)
1 pcs
0.23lb (105g)/pcs

S8901-54XC Hardware Installation Guide | 6
Component Physical Information
Specification
Item
Description
Weight
Total package contents
34.17lbs (15.50kg)
Chassis without FRU
19.18lbs (8.7kg)
Power Supply Unit (PSU)
DC PSU: 2.2lbs (1.0kg)
AC PSU: 2.6lbs (1.2kg)
Fan module
0.41lbs (185g)
Grounding lug kit
0.037lbs (17g)
Adjustable mounting rail
0.69lbs (315g)
USB 3.0 cable
0.04lbs (17.2g)
AC power cord (AC version only)
0.72lbs (325g)
RJ45 to DB9 female cable
0.23lbs (105g)
Dimension
S8901-54XC (W x D x H)
17.32” x 17.32” x 1.72”(440 x 440 x 43.8mm)
PSU (W x D x H)
1.99” x 8.30” x 1.57” (50.5 x 211 x 40mm)
Fan module (W x D x H)
2.03” x 1.66” x 2.28” (51.5 x 42.2 x 57.8mm)

S8901-54XC Hardware Installation Guide | 7
4Identifying Your System
S8901-54XC System Overview
Figure 5.

S8901-54XC Hardware Installation Guide | 8
DC Version PSU Overview
1+1, hot swappable power supply unit (PSU) field replaceable unit (FRU). There are two types of DC
PSUs. The picture on the left is the DC PSU with back-to-front airflow, identified with a blue latch.
The picture on the right is the DC PSU for front-to-back airflow, identified with a red latch.
Back-to-Front Airflow PSU
Front-to-Back Airflow PSU
Figure 6.
The DC power supply units are the same size for both back-to-front airflow and front-to-back
airflow. Therefore, only the dimensions for back-to-front airflow PSU will be provided in the figure
below.
(Back-to-Front Airflow PSU)
Figure 7.
Inhaltsverzeichnis
Andere UfiSpace Schalten Handbücher