Theequipmentmustbeinstalledinaccordancewithinstallationrequirementsoftheauthorityhaving
jurisdictionor,intheabsenceofsuchrequirements,tothecurrenteditionoftheNational Fuel Gas Code, ANSI
Z223.1/NFPA 54.
Where required by the authority having jurisdiction, the installation must conform to American Society of
Mechanical Engineers Safety Code for Controls and Safety Devices for Automatically Fired Boilers, ASME CSD-I.
Carefully read these instTuctions before beginning work. Understand all aspects of the installation. Contact your Peerless Heater
Company sales representative or customer service for help in answering questions.
This boiler must be installed by a qualified contractor. The boiler warranty can be voided if the boiler is not installed correctly.
r,_! P__] =k'-]_'tlHI l|&'J IN I!__,I ;5_,1=_IN =[<
Install boiler not less than 24" between the top and front
of the boiler and adjacent wall or other appliance, when
access is required for servicing. Do not install boiler on carpeting. Boiler installation
on carpeting is a fire hazard,
_e,]l [e,Zo]L'r_l:tlj.:']ld[o]_'Hf_,lL'111]Lrj:l_'_llllf,_'l/[o]L'_|:!l;
The design of this boiler is certified for alcove installation
with the following clearances from combustible
construction:
I Sides: 2"
2. Top of Jacket: 36"
3. Draft Hood: 6"
4. Vent Pipe: 6" (1" for Type B vent)
5. Rear of Jacket: 6"
Do not install this boiler on combustible flooring.
Boiler installation on combustible flooring is a fire
hazard.
6. If it is necessary to build a non-combustible floor pad
over top of an existing combustible floor, construct
pad as stated in the .National Fuel Gas Code
Handbook Part 6, Installation of Specific Equipment.
].
2.
Provide adequate facilities for combustion and
ventilation air in accordance with Section 5.3, Air for
Combustion and Ventilation, .National Fuel Gas
Code, or applicable provisions of the local building
code. Subsections 2 through 6 below are based on
National Fuel Gas Code requirements.
Definitions:
Unconfined Space: a space whose volume is not
less than fifty (50) cubic feet per 1000 Btu!hr of the
total input rating of all appliances installed in that
space. Rooms communicating directly with the space
in which the appliances are installed, through
openings not furnished with doors, are considered
part of the unconfined space.
Unusually Tight Construction: Construction
where:
a. Walls and ceilings exposed to the outside
atmosphere have a continuous water vapor
retarder with a rating of 1 perm or less with
openings gasketed or sealed, and
b. Weatherstripping has been added on openable
windows and doors, and
e. Caulking or sealants are supplied to areas such
as joints around window and door frames,
between sole plates and floors, between wall-
ceiling joints, between wall panels, at
penetrations for plumbing, electrical and gas
lines, and at other openings.
3. Appliances Located in Unconfined Spaces:
For installations in unconfined spaces with other
than unusually tight construction, the supply of air
for combustion and ventilation can usually be
considered adequate.